Construction Update as of Wednesday, August 18, 2010
- 300 Block of Aberdeen Street SE
- Roadway is paved and open to public traffic.
- 400 Block of Aberdeen Street SE
- Road closure currently in use.
- Road coring, base gravel preparation, and placement of asphalt
– Estimated date of completion is Friday, August 27, 2010. - 500 Block of Aberdeen Street SE
- Roadway is paved and open to public traffic.
- 4 Avenue between Aberdeen Street SE and Belfast Street SE
- Roadway is paved and open to public traffic.
Contact Information:
Jamie McLeod
City of Medicine Hat, Project Manager
Environmental Utilities Department
(403) 502-8596