CDV – 2025-2032 TCA – Theatre Seat Replacement: What will be done with the seats that are removed? Is there any opportunity to recover costs associated with this project? |
The seats will likely be disposed in a safe manner unless a donee is identified. Donating seats can be complicated as theatre seats require additional cost to reconfigure the floor for the installation.
Opportunities to recover costs associated with the project would be grant fund opportunities.
|
Why was CDV - 2023 TCA - Bar Installation at Co-op Place considered a priority in the 2023-24 budget? |
A portable bar was used to serve highballs on a trial basis for events. The drink station helps reduce lineups and increase convenience. We know drink availability is a big contributor to patron satisfaction and are high margin sales items. However, the portable unit was deemed inadequate for a number of reasons. There is no running water (ie. handwashing and cleaning station) nor access to sewer so all liquid needs to be removed from the area manually. Stock has to be moved in and out for every event. This project will rectify those concerns allowing us to maintain the benefit of an additional drink service location. |
COP FM 2023 - Crestwood Pool Components Lifecycle: Is there funding in this 2023-24 capital budget to assess the future of the Crestwood Pool facility? |
The 2023-24 Capital Budget, includes various small lifecycle management of various infrastructure items which are intended to extend the useful life of the facility 10 to 15 years and is intended to maintain the facility in operating order while corporate recreation planning activities continue through finalization (e.g. a pool liner versus wholesale pool tank replacement, some air handling unit replacements and related duct work, and miscellaneous small plumbing upgrades). Further investment will be required should City Council determine that this facility should remain open beyond the 10-year planning envelope.
The scope does not include any studies pertaining to the Facilities for the Future initiative currently being led by the Parks and Recreation department. That initiative will feed into future infrastructure planning in future budget cycles and is not intended to be funded from this capital budget.
|
COP FM 2023 - Crestwood Pool Components Lifecycle: Just a question about timing of this project. I am hoping that Substation-11 may be complete or nearing completion by that time, which would mean we could potentially begin construction on a new south side recreation facility. Is this project timeline flexible based on those factors, along with anticipated failures at Crestwood? |
The anticipated completion date of Medicine Hat Substation 11 will be end of 2025 assuming the Alberta Utilities Commission approves one of the proposed locations. If both locations are denied then City Operations will need to restart the entire approval process thereby delaying the substation by 2.5 to 3 years (for early 2028 completion). Regarding Crestwood, City Operations continues to work closely with Parks and Recreation on their Facilities for the Future project. Capital work/projects pertaining to Crestwood pool will be carefully planned to coordinate activities to ensure the optimal use of public funds. Projects currently planned at this location are designed to extend the useful life of the facility to enable City Council time to debate the ultimate plan for Crestwood. City Operations will not initiate projects at this location without detailed conversations with Parks and Recreation to ensure we are not expending unnecessary funds. Therefore, we do see the timing of execution as flexible but still highly recommend funding remain in place to ensure adequate resources are allocated should we experience another unplanned failure at this location. |
Please explain more about "COP - FLT - 2023 - Mobile Capital" and "COP - FLT - 2024 - Mobile Capital." Has Mobile Capital been funded in a similar way and amount in the past? |
These projects represent the annual Fleet replacements. The budget process has not changed from the past, but the presentation of the budget changed. Instead of listing each individual unit that is up for renewal, the total amount required for Fleet replacements is what is presented for approval. The detailed listing still exists with Fleet as the basis for the lump sum amounts each year. |
PKRC - 2023/2024 TCA - South Saskatchewan River Recreation Opportunities: Is this part of the Downtown plan or a different focus entirely? Is 2023 for studies and 2024 for implementation of recommendations from the study? |
This project is to upgrade the boat launch at Echo Dale Regional Park. It was identified in the 2015 South Saskatchewan River Recreation and Leisure Plan. We have seen increasing activity on the river that starts upstream at Echo Dale and therefore increasing access capability and safety has become an increasing priority. |
Is there an overlap between the Transportation Infrastructure Rehabilitation Program (23210672) and the Airport projects for Detailed Design (24210511) and Construction and Groundside Access Improvements (24210510)? |
The Transportation Infrastructure Rehabilitation Program mainly addresses the need to repair/rehabilitate existing roads, sidewalks, etc. There are plans in the 2023-24 Transportation Infrastructure Rehabilitation Program for geometric upgrades at two intersections along Gershaw but upgrades to Airport infrastructure are not addressed within this program. This program is not for asset management but for improvements to the existing intersection designs and forms part of the Roadway System Master Plan execution strategy for specific locations. The Department will engage with Stakeholders and Residents in the process of executing/continuing this program. |
What is the Laneway Rehabilitation Project (23210684)? |
Laneway and sidewalk rehabilitation forms part of the City’s overall Asset Management Strategy focusing on roads, lanes and sidewalk rehabilitation and resurfacing. This program consists of lane overlays and structural rehabilitation. |
What is the Bridge Rehabilitation Project (23210674)? |
The city is responsible for 21 bridges and culverts in accordance with the Canadian Bridge Code. This program is for ensuring the city adheres to Federal and Provincial requirements for Bridge Management. The city works closely with Stakeholders like Alberta Transportation where applicable. |
What is the Bridges and Boardwalks Infrastructure Program (32610657)? How does it differ from the Bridge Rehabilitation Program (23210674)? |
The Bridges and Boardwalks Infrastructure Program is lead by our Parks and Recreation Department while the Bridges rehabilitation program is lead by City Assets. The Parks department is primarily accountable for bridges and trails within city parks. The program includes assets such as bridges (timber structures and/or steel structures with timber crossings) with railings, timber boardwalks (no railings), and corrugated steel pipe (CSP) culverts with earth berms and asphalt. These permit trail utilization over water bodies, groundwater seepage areas, and elevated areas over undulating ground. |
What is the Trail Infrastructure Program (32610650)? |
For 2023, the trail infrastructure rehab program seeks to replace all trails that are considered in very poor condition as well as replacing 16% of the trails in poor condition. The city has over 160 km of trails within its jurisdiction with an estimated replacement value of $35 million. As outlined in the “Informing the Future – Canadian Infrastructure Report Card”, trails have a targeted rate of reinvestment at minimum of 2% per year with an upper target reinvestment rate of 3% per year. Our plan represents a replacement value of 2.5%, perfectly within the benchmark standard for replacement. The Parks and City Asset departments work closely to ensure best practices are followed regarding the use of city equipment and human resources. |
What is the Multi-modal Transportation Connectivity Plan (23210675)? How does this differ from the Transportation Safety Plan (23310511)? |
By contrast to the Transportation Safety Plan (23310511) which is a Major Operating Expense, this project is for the purchase of capital expenditures. This project will improve connectivity within the pedestrian network by constructing sidewalks in deficient areas as well as expand uses to include multi-modal forms of transportation in areas where applicable. Also, improved accessibility will be realized with construction of wheelchair ramps where required. This project will help reduce a safety risk by creating a more pedestrian/multi-modal friendly environment and help improve the overall health and wellness of citizens. This project includes installation of new sidewalks and multiuse trails where needed. Priority areas include the hospital area, near school zones, and areas where infrastructure is needed to connect existing infrastructure. … This project also includes construction of new wheelchair ramps to be installed at appropriate locations in deficient areas. |
How does the Active Transportation Plan compare to the Roadway System Mater Plan? |
The Roadway System Master Plan (RSMP) outlines the City’s transportation network requirements into the future based on population projections from the municipal development plan. The RSMP identifies the class of roads and location of roads that will be required to adequately handle traffic volumes as the city population grows. The Active Transportation Plan deals with the emerging use of multi-modal transportation options such as cycling, e-scooters, roller blades, etc. The ATP is a planning document that outlines “where (network location), when (implementation schedule) and what (on or off road)” needs to be established to develop an effective multi-modal network that provides safe, efficient infrastructure for all users. The Transportation Safety Plan deals with safety issues associated within the entire transportation network including vehicles, pedestrians, and multi-modal users. The TSP will identify the safety issues and provide a toolbox of potential mitigative measures. For example, speeding in residential areas addressed through a reduction in posted speed combined with traffic calming measures. |
What is the Drainage and Erosion Remediate Infrastructure Program (32610654)? |
Northwest Riverside Trail is a very popular trail and is part of the primary active transportation route. Due to overland drainage as well as river scour/erosion, the bank is eroding and the trail is subsequently sloughing into the South Saskatchewan River. The drainage and erosion program focuses on identifying locations of highest concern, engineering/design, all regulatory approvals, and mitigation. |
What is the South River Bank Improvement Program (21610559)? |
The purpose of this project is to protect the WWTP from infrastructure and property damage, should the South Saskatchewan River experience a 1:100 year flood. A 2018 study by MPE identified approximately 450 metres of the South Saskatchewan Riverbank immediately adjacent to the WWTP that should be protected in three construction stages. Stage 1 and 2 are identified to be completed simultaneously for 2024, while stage 3 is listed for 2025. This project involves upgrading the river bank with riprap armoring in order to protect the WWTP during flooding. |
What is the Transportation Infrastructure Rehabilitation Project (23210672)? |
This project is the City’s Rehabilitation program for vehicular, pedestrian, cycling, rail and air related transportation infrastructure. This includes various forms of asset management to address deteriorating transportation infrastructure. These projects leverage maintenance as often as possible to reduce the need for full roadway replacement projects. Eventually, full road replacement will become necessary, and the City invests where possible to reduce expensive and disruptive projects. |
What is the Dunmore Road Rehabilitation Project (23210679)? |
This project is specifically for Dunmore Road pavement surface rehabilitation. Typically, these are larger corridor projects that include asset management rehab, but may also include capacity upgrades or surface enhancements that are not considered infrastructure asset management. |
What is the South Boundary Road Rehabilitation Project (23210681)? |
This project is specifically for South Boundary Road pavement surface rehabilitation. Typically, these are larger corridor projects that include asset management rehab, but may also include capacity upgrades or surface enhancements that are not considered infrastructure asset management. |
What is the College Avenue Bridge and Kipling Intersection Project (23210705)? |
This project includes substantial redesign of the existing culvert crossing and intersection to improve creek flow and traffic congestion that is anticipated as the city population grows. |
What is the Industrial Ave Bridge Replacement Project (23210707)? |
This project is a full bridge replacement as the existing bridge is reaching its end of life. |
What is the Day Street Bridge Replacement Project (23210708)? |
This project is a full bridge replacement as the existing bridge is reaching its end of life. |
Why, in certain cases, is future funding for a particular project listed as separate projects? |
In general, future funding for a particular project may be listed as a separate line items if the funding is not needed until after the budget cycle. This prevents the city from tying up its capital funding in its 2023-24 budget for projects that will not experience cash outflows until future periods. In other cases, certain grant programs (e.g., ICIP) require that there is a separate line items for each year of a project. |