Hillside Irrigation Replacement
Project Description
Aging irrigation lines in Hillside Cemetery must updated to maintain the City's service standard.
To best accommodate visitors, construction will be completed in phases over several years.
Start Date | End Date | |
---|---|---|
Phase 1 (NE irrigation & columbarium) |
August 2020 |
June 2021 |
Phase 2A |
Late spring 2021 |
April 2022 |
Phase 2B |
Summer 2021 |
Expected June 2022 |
Phase 3 |
Anticipated spring 2022 |
End of 2022 construction season |
Phase 4 |
Anticipated spring 2023 |
End of 2023 construction season |
Phase 5 |
To be determined |
Timing & Traffic Accommodations
Visitation hours may be modified for anyone wishing to visit this area of the grounds.
A detour for vehicles through the grounds may also be in place.
Construction site map will be available at the Hillside Cemetery main office for questions or concerns.
Benefits
The current irrigation system requires ongoing repairs due to the age of the system.
An updated system will require less maintenance and help to maintain the large urban forest.
Notifications
Information for visitors will be available at the gate and Hillside Office.
Updates will be posted on the City's social media accounts, as well as this page.
Safety
Signs will be placed in the area where crews are working. Please allow crews room to work.