Riverside Overland Flow Protection Strategy is designed to protect the residential community of Riverside along Parkview Drive and 1st Street NE/NW from overland flooding during high flow events on the South Saskatchewan River. The project is currenlty in the preliminary design phase. There is an added level of complexity to the project given the proximity of private residences to the rivers bank. The land south of 1st Street NE/SW is owned by the adjacent property owner and thus nogotiations with the land owners are required.


Key Project Milestones and Schedule
Stage Project Stage Estimated Completion Date
I River/Creek Modelling January 2014
II Preliminary Design December 2014
III Detailed Design Spring 2015
IV Tendering
Contract awarded to
TBD
TBD
V Construction TBD

Public Information Session Open Houses
Date Location Time
March 24 & 25, 2014 Higdon Hall, Stampede Grounds 4 - 8 pm    
May 6, 2015                  Cutbanks Room, Esplanade        4:30 - 6:30 pm 
July 13, 2016 Cutbanks Room, Esplanade 4:30 - 6:30 pm