New Seniors Centre

Print
Press Enter to show all options, press Tab go to next option

Latest News

Date Information
 December 7, 2017 

Photo Gallery  

 

Completed

Vapour Barrier

Flat Roofing - Board, Vapour Barrier

 

Ongoing

Interior Steel Stud Framing

Plumbing Rough-in's

Ducting Rough-in's

Electrical Rough-in's

Clips/Cladding/Insulation

Metal Roofing

 

Scheduled Next

Aluminum Frames

Glass Install

 October 31, 2017

Conduit installed and wire pulled in basement

Ductwork has been installed in basement

Gas main has been installed

 

Installing conduit on main floor

Installing ductwork on main floor

Installing sprinkler piping on main floor

Installing exterior window and door frames

Sheeting and wrapping exterior

Sheeting roof

Prepping gravel base for north parking lot

Curbs being poured

 

 October 12, 2017

Miscellaneous steel erection 

Metal decking installation 

Framing and sheathing

Concrete encased ductwork

Slab on grade prep

Exterior wall framing 

Underground plumbing 

Electrical rough ins

 August 31, 2017 

Concrete foundations and grade beams are completed
Foundation backfill is completed
Deep service installation is ongoing and almost complete
Structural steel is being erected
Wood trusses and sheathing are being installed and constructed 

 July 26, 2017 

Demolition is done and construction has begun!  The contractor has constructed new sanitary and water service stub outs, they've begun structural construction of pad footings and screw piles and even have some new framing up for some walls.

June 26, 2017

Work is progressing with select demolition of the interior and exterior of the Veiner Centre. You will see that the roof is currently being removed and the entire East side of the building should be demolished to the foundation within the next couple of weeks. Demolition of the Lion’s Kitchen is underway to be replaced by another kitchen and washrooms on the North side of the building that will be part of the new Seniors Centre building itself. 

May 2, 2017 

A great crowd of City officials, members of the Senior Citizens Advisory Committee and project staff were on hand for the official sod turning at the Veiner Centre site of the  Seniors Centre Redevelopment Project. 

November 2016 

Updated detailed designs of the Seniors Centre Development Project were shared with the public at an open house at the Strathcona Centre on Nov. 28. Attendees were able to ask staff and the architect questions, see site plans and floor plans, and learn more about the project.

Seniors Centre Development

Veiner Centre 

Strathcona Centre

October 2016

Detailed design of the project is approximately 60% complete. Revisions to the design will be shared with the public at an Open House scheduled for November 28, 2016 from 4 p.m. to 8 p.m. at the Strathcona Centre.

Changes to the design have been made as a result of the input and comments from the Open House in June, which included discussion on the trees, pathways etc. from the nearby home owners. The project continues to be on schedule, and the next major steps include tendering the work in January / February 2017, with the intent to start the actual construction in the spring.

 

August 2016 

Council approved the Seniors Centre development design for the Veiner Centre and Strathcona Centre at its Aug. 2, 2016 meeting.

Staff worked with FWBA Architects to create a design that would maximize the use of the current Veiner Centre main floor, minimize the size of required expansion and take advantage of the Strathcona Centre for specific functional programming. A combination of renovated space, demolition/construction and new expansion will occur at the Veiner Centre building. 

• Senior Centre design (PDF) 
• Senior Centre walk through video (YouTube)

Council also approved a Seniors Centre development construction budget of $11.6 million. This project will be funded using the $1.46 million received from insurance and $10.14 million funded by debenture. 

At the meeting, Council also directed staff to examine alternative models, along with the associated costs, for operation of the Seniors Centre. 

City staff will continue forward with FWBA Architects to commence work on detailed design and construction drawings, which are anticipated to be complete in October 2016.


July 2016

Design development continues.

Bring forward formal capital budget amendment through Public Services Committee (targeting July 25) to City Council (targeting August 2).

 

June 2016

Met with SCAC and Building Committee representatives on June 7 and 14 to review proposed site plans, floor plans and basic building elevations and receive feedback.

Provided design briefing to City Council members.

On June 27, provided opportunity for nearby property owners along Woodman Ave and Washington Way to view and comment on site plans.

Initiated discussion with Lions Club regarding Veiner Centre expansion plans and potential impact upon existing Lions Kitchen.

Proposed site and floor plans circulated to City technical departments for preliminary comment prior to development permit application.

Design development continues.

 

Click here for archive.