August 2017

Print
Press Enter to show all options, press Tab go to next option

<< Back

  • Concrete foundations and grade beams are completed
  • Foundation backfill is completed
  • Deep service installation is ongoing and almost complete
  • Structural steel is being erected
  • Wood trusses and sheathing are being installed and constructed

Seniors Centre Redevelopment - August 2017