Crescent Heights Lift Station Project Update

Print
Press Enter to show all options, press Tab go to next option

Trail reinstatement and landscaping targetted for end of spring

Spring 2019 Update: 

Reinstatement of the trail through the construction area is targetted for the end of spring, 2019. 
Completion of the surface works including landscaping and paving of the trail require consistent good weather, both for trail access and to ensure asphalt can be used and properly set. Please continue to obey signs and barricades until this work is completed.

Public Safety is important to the City. 

  • Until the pathway is reinstated, entry is prohibited
  • Please avoid this area, and obey the signs and barricades in place for your own safety. 

We realize this is a popular trail and thank everyone for their extended patience.

 

December 2018 Update:

The construction of the new Crescent Heights Lift Station and associated infrastructure is completed, and the facility is now fully operational. The Crescent Heights Lift Station serves approximately 15% of the City’s population, including Riverside and most of Crescent Heights. Wastewater services were maintained seamlessly throughout the project, without disruption to customers.

 Parkview barricade  ppp barricade

 

IMG_4897


The project included substantial underground infrastructure as well as the above-ground facility:

  • Construction of a vault to store waste water and pumps that start automatically, sending it to a force main
  • Installation of two kilometers of newly completed underground pipeline, transporting waste water to the Wastewater Treatment Plant
  • Construction of the above-ground building that houses important controls, sensors and a back-up generator
  • Demolition of the original 1961 lift station facility

Project Details and Benefits

The Crescent Heights Lift Station serves approximately 15% of the City’s population, including Riverside and most of Crescent Heights. The project included:

  • Construction of a large underground vault which houses submersible pumps that convey wastewater to the Wastewater Treatment Plant
  • Installation of two kilometers of 750mm forcemain which ties into the existing wastewater system
  • Construction of the above-ground building that houses electrical and mechanical controls and a back-up generator so the facility can maintain operation during utility power failure
  • Decommissioning and demolition of the original 1961 lift station facility

 

This new lift station facility is part of the City’s flood mitigation strategy which includes relocation of three existing lift stations to higher elevations where they can continue to operate in flood situations.

Thank you for understanding and respecting the trail’s closure during the project, which will provide benefits for many years to come.

For more information:
Environmental Utilities
403.529.8176